Elita Garden Vista Progress Update

20 November 2008

Block 1 : Shuttering, reinforcement and concreting work of 4th floor level slab is in progress

Block 2 : Shuttering, reinforcement and concreting work of 3rd floor level slab is in progress

Block 3 : Shear wall work above 2nd floor level slab & Staging , shuttering work for 3rd slab is in progress

Block 4 : Reinforcement work for grade slab work is in progress

Block 5 : Shear wall work upto grade slab is in progress

Block 13 : Tie beam work at (-)800 level in progress

Block 12 : Tie beam work at (-)800 level in progress

Block 14 : Back filling & grade slab work is in progress

Block 11 : Pile cap work completed

Block 7 : Pile cap work in progress

Block 15 : Shuttering, reinforcement and concreting work of 1st floor level slab is in progress

Block 16 : Staging, Shuttering and reinforcement work of 1st floor level slab is in progress

Block 10 : Pile cap work in progress

Block 9 : Pile cap work in progress

Block 8 : Pile cap work in progress

Boundary wall (front side) in progress

External access road (HIDCO road)

External access road (Shapoorji side)

Assembly Area for Safety & Health Promotion Week

Internal access road to mock up units completed

Internal access road for Phase 2 blocks

Piling work for Tower-crane in progress