 Block 1 : Shuttering, reinforcement and concreting work of 4th floor level slab is in progress |
 Block 2 : Shuttering, reinforcement and concreting work of 3rd floor level slab is in progress |
 Block 3 : Shear wall work above 2nd floor level slab & Staging , shuttering work for 3rd slab is in progress |
 Block 4 : Reinforcement work for grade slab work is in progress |
 Block 5 : Shear wall work upto grade slab is in progress |
 Block 13 : Tie beam work at (-)800 level in progress |
 Block 12 : Tie beam work at (-)800 level in progress |
 Block 14 : Back filling & grade slab work is in progress |
 Block 11 : Pile cap work completed |
 Block 7 : Pile cap work in progress |
 Block 15 : Shuttering, reinforcement and concreting work of 1st floor level slab is in progress |
 Block 16 : Staging, Shuttering and reinforcement work of 1st floor level slab is in progress |
 Block 10 : Pile cap work in progress |
 Block 9 : Pile cap work in progress |
 Block 8 : Pile cap work in progress |
 Boundary wall (front side) in progress |
 External access road (HIDCO road) |
 External access road (Shapoorji side) |
 Assembly Area for Safety & Health Promotion Week |
 Internal access road to mock up units completed |
 Internal access road for Phase 2 blocks |
 Piling work for Tower-crane in progress |